Wanted to know the impact if we change the Global Date Format

Arpita Argulwar May 5, 2014

Hello Team,

If we change the global setting for the date format from dd/mm/yy to dd/mm/yyyy what will be the impact for existing field's values, existing report with date field and any other.

Jira Version is 3.13

Thanks,
Arpita Argulwar

1 answer

2 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 5, 2014

The dates will be displayed in the new format once you change the configuration. All dates are stored as date-time in the database and hence the data won't be corrrupted. They just will be rendered differently.

Arpita Argulwar May 5, 2014

What abt the existing reports?

Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 5, 2014

Depends on what you mean by "reports". If you mean the filters, you may have a problem if people have specified real dates as the filters may not interpret the old strings correctly any more.

But date settings (where you are asked for a date or date range) will be fine because they store and use dates in the background and all you've done is change the display and entry methods. Things like Jira reports, Gadgets, and so-on, should still work.

Arpita Argulwar May 6, 2014

Thanks a lot Jobin abd Nic! It's all that I required.