I have multiple boards set up exactly the same way for different projects. One of them shows the total number of issues, remaining time, and original estimates for a couple of sprints but not all of them. Other boards don't show this info at all. It's very helpful and people are asking me ot add it to all sprints on all boards. I'd love to but I can't for th elife of me figure out how. Does anyone know if there is UI somewhere for me to control this and if not, what the rules are for when it does and doesn't show up?
Thx!
Hi Kathy,
If you go to Board > Configure > Card Layout you can modify what is shown on your board:
Cheers,
Branden
Do those setting impact the totals (highlighted in yellow in my screen shot) at the bottom? I played with them but they only seemed to effect the fields that show up on the actual cards, not a summary line at the bottom.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.