Version Start date and end dates can be changed anytime. Can we set any restrictions like

1. Configure such that one cannot the change the dates once set

2. Or only few authorised people are able to change means we make it permission oriented

3. Or ANy changes in dates of version are recorded for audit purpose.

2 answers

0 votes
Theodore Tzidamis
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 10, 2012

On a small note: There is a feature request about having audit logs for version changes

Feel free to vote/comment/watch that issue, if you like. ;-)

Cheers,

Theo

0 votes
cgauterio
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 5, 2012

Hi Shampa,

Unfortunately there is no way to restrict that. Any user that has the JIRA 'Project Administrator' permission in the relevant project can create versions in Greennhopper.

Cheers,

Clarissa Gautério