When I click in a specific sprint, values shown in the grid and on completed columns seems not be right.

sample:

 

XMI-153xxxxBugMediumDONE1
XMI-190xxxxxBugMediumDONE-
XMI-284 *xxxxxStoryMediumDONE-
XMI-291xxxBugMediumDONE-
XMI-323 *xxxBugHighestDONE1

 

But If I click for instance on XMI-190, it will show me story point 2.

 

Is there anything I´m missing here?

 

Thanks

1 answer

0 votes
Paulo Junior
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 6, 2015

Hi Orlando,

Have you estimated the Story Points after the Sprint has started? Please note that Velocity doesn't consider Story Points attributed during the sprint.