Upgrade JIRA 4.0.1 to JIRA 6

Zhang Jian September 16, 2013

We are planning to upgrade our old JIRA sysem from 4.0 to latest version, May I know the steps to do so and what need to be prepared?

Thanks.

2 answers

0 votes
AlaA
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 17, 2013

Hey Zhang,

Basically, the steps to be followed are:

  1. Take the XML backup of your 4.0 instance
  2. Set-up the latest version of JIRA (which is now 6.0.8)
  3. Copy over the Attachment folder from your old JIRA to the new JIRA
  4. Copy over the installed-plugin folder from your old JIRA to the new JIRA
  5. Perform the importing process.

It's always advisable to perform the upgrading process in a test instance first, before you do it in your production instance.

I hope that was helpful.

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 16, 2013

Start with https://confluence.atlassian.com/display/JIRA/Upgrading+JIRA

I always recommend reading ALL the release notes for every mid-level version you will be jumping (i.e. 4.1, 4.2, 4.3, etc)