Update sub-task status to match parent's

Hi All,

On some instances I want to move an issue from one status to another, with it's child/sub-tasks issues following it in status.

Is this possible? 

Kind Regards,

Anis Ahmed Chohan

1 answer

You can add an Update issues post function (part of Update on Transition for JIRA) to the transition. In the post function you define a JQL query to determine all the other issues that need to be transitioned - see How to use JQL to find issues to update. For information on how to use update issues to do a transition, see Transition issues.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

2,950 views 12 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot