Update custom field value with Current_DateTime + e.g. 7 days

Michael Reiff June 28, 2015

How can I add e.g. 7 days to the current date.

I wand to update a custom Field (Field Type: Date picker) with a Postfunction of the JIRA Suite Utiliy: Update Custom Field Value?

 

3 answers

0 votes
Sateesh Chandra
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 29, 2015
0 votes
Michael Reiff June 29, 2015

Thank for your help: The custom Field of Type "calculated Date" is my Resolution.

0 votes
Sateesh Chandra
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 28, 2015

You will need to use the Transition Date/Time Field

  • Create a new custom field, choosing "Transition Date/Time Field" for its type
Michael Reiff June 28, 2015

I can't find the custom field type: Transition Date/Time Field To be more clear: I want to add e.g. 7 days to the current date, using the Postfunction "Update Custom Field".

Sateesh Chandra
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 28, 2015

It is not possible to add days using "Update Custom Field" post-function. You can only set it to current date value.