Under JIRA portfolio will the information auto update if working in a project and a date changes?

We currently don't have portfolio but wanted to see if the information will update if we change it on the project page; i.e. changing an end date.  I don't want to have to update dates in two places.  Thanks.

1 answer

1 accepted

This widget could not be displayed.

Hi @Courtni Holdegraver,

 

Most of the information in Portfolio for JIRA plans are pulled from JIRA and as such should not require you to change in multiple places.

The due date field (if that's the one you are using for "end date" in JIRA is not used in Portfolio as it calculates its own start/end date.

It might help figuring out the best usage for you if you could further describe the problem that you are trying (or expect) to solve with Portfolio.

 

Cheers,

Thomas

Thanks for the feedback. To further explain I want to create a roadmap in portfolio but not want to update in two places, for example if the end date changes my roadmap will auto update. 

Also on a side note has portfolio gotten better with print capabilities? 

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

217 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you