Transition Sub Task from Parent issue

How do I have my sub task automatically transition into the "done" status after I transition my parent task issue into the done status? 

 

I have the Automation add-on but I'm confused when I get to the copy from parent selection or which JQL I should use for the sub task. 

1 answer

1 accepted

0 votes
Accepted answer

Had to use the branch rule inside of the Automation add-on.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,748 views 18 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you