Tracking Changes in Due Date

MIke Madore October 15, 2013

How can we track and report changes in an issues Due Dates? Is there a Baseline or Original Due Date? I would like to include issues with changed due dates on dashboards and management reports showing the original (baseline) due date and the new (planned) due date. The purpose is to identify issues that are slipping to facilitate discussion of the reasons for the slip.

2 answers

1 accepted

1 vote
Answer accepted
Sergio October 20, 2013

I'm not sure if you can have a dashboard showing that, because JIRA doesn't allow you to use issues' history (change log) in filters. However, you can use REST API to get it.

Have a look to this:

https://jira.atlassian.com/browse/JRA-27692

Cheers

Sergio

0 votes
MIke Madore October 27, 2013
We are using Gant Chart for JIRA to track projects