Tracking Changes in Due Date

How can we track and report changes in an issues Due Dates? Is there a Baseline or Original Due Date? I would like to include issues with changed due dates on dashboards and management reports showing the original (baseline) due date and the new (planned) due date. The purpose is to identify issues that are slipping to facilitate discussion of the reasons for the slip.

2 answers

1 accepted

This widget could not be displayed.

I'm not sure if you can have a dashboard showing that, because JIRA doesn't allow you to use issues' history (change log) in filters. However, you can use REST API to get it.

Have a look to this:

https://jira.atlassian.com/browse/JRA-27692

Cheers

Sergio

This widget could not be displayed.
We are using Gant Chart for JIRA to track projects

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

174 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you