Time tracking settings

Anders Nilsson August 5, 2014

Hi all!

How will the current time estimates be affected if whe change the numbers below to eight working hours a day and five days a week? Will they be recalculated in a correct way? Eg a time estimate that is 24h today will be 3 days?

/Anders

1 answer

1 vote
Yit Wei
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 13, 2014

Hi Anders

All existing time estimates will be readjusted. For example, if logged work is originally set as 1d (24h), when you change the working hours to 8 hours a day and 5 days a week, the logged work will be changed to 3d.

Suggest an answer

Log in or Sign up to answer