Time tracking settings

Hi all!

How will the current time estimates be affected if whe change the numbers below to eight working hours a day and five days a week? Will they be recalculated in a correct way? Eg a time estimate that is 24h today will be 3 days?

/Anders

1 answer

Hi Anders

All existing time estimates will be readjusted. For example, if logged work is originally set as 1d (24h), when you change the working hours to 8 hours a day and 5 days a week, the logged work will be changed to 3d.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Jira

5 ways you can make the most of Jira Software and Bitbucket Cloud

As part of the Bitbucket product team I'm always interested in better understanding what kind of impact the use of our tools have on the way you work. In a recent study we conducted of software devel...

63 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you