Time Tracking Remaining

 After  logging work on ISSUE , Remaining is updated . However, after logging work on Issue's Sub-Task  the Remaining is not change

What do I miss? 

 

Yoram

1 answer

0 vote
Micky Caritte Community Champion Jan 09, 2018

Hi Yoram,

Actually Jira considers each task as an independant task, even if subtasks are highly linked to their parent. it means that time tracking is not shared with subtasks (a Task can have an objective by itself, not only be a container). That being said, there must be a checkbox allowing you to include subtasks in your time tracking from a parent, if you do so, it will sum up all subtasks and current task times (logged, remaining, estimates) in a consolidated view. You can get more details here:

https://confluence.atlassian.com/jirasoftwarecloud/logging-work-on-issues-902499028.html

Hope this helps!

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Jira

5 ways you can make the most of Jira Software and Bitbucket Cloud

As part of the Bitbucket product team I'm always interested in better understanding what kind of impact the use of our tools have on the way you work. In a recent study we conducted of software devel...

64 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you