Time Tracking Chart shows wrong Estimated Time

The estimated time bar should be completely filled blue. Anyone an idea?

1 answer

1 accepted

3 votes
Accepted answer

Hi, the whole bar is the total. THe total currently = logged + remaining, which is 9d. The estimate is 5d 5h, which is where it is now. In this example, you have logged more than estimated and then removed some days or similar. When you have removed time logged you would have been given options as to what to do with this change.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,716 views 17 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you