Time Spent on Burndown Chart

Aamer Inam: M-3521 September 22, 2014

Hello ,

 

I need to know in case there is an issue for which we do not specify original or remaining estimate and use log work against that item, does this time spent shown on the overall burndown chart and this particular item is part of the current sprint.

Look forward to your kind response.

Regards,

 

1 answer

0 votes
Luther Hargrove
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 22, 2014

If you change the estimations to be %Complete then this will work just fine.  That is the only way to get your burndown to show the data you want it to.

Aamer Inam: M-3521 September 22, 2014

where do we change this setting?

Aamer Inam: M-3521 September 23, 2014

@Nicolas Nicolas can you please help in this regard.