The value of Resolved to Closed KPI is wrong

Dnyaneshwar Ramesh Borase March 13, 2017

We are using the JIRA Enhancer plugin for defect management purpose.In Time between field We have set KPI as a Resolved_to_Closed custom field. While doing the defect analysis we observed following for some defects;

  1. The Resolved to Close is -124 hrs this value cannot be correct.
  2. The value of Resolved to Closed KPI is wrong. its coming 149 hrs whereas it should come around 87 hrs
  3. Why it is showing negative value?

    Please let me know why this is coming up?

    Thanks,
    Swapniashilpa

2 answers

0 votes
Tuncay Senturk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 14, 2017

Hi,

Could you please share Time Between configuration and the issue's history (All tab in issue main view)?

Also, if you raise a ticket here, we'll soon fix the problem and you'll get notified about the progress.

Regards

Tuncay

Dnyaneshwar Borase March 14, 2017

Thanks Tuncay.

As suggested, We have raised a ticket for this issue.Please refer the link of raised ticket

https://bitbucket.org/tuncaysenturk/jira-enhancer-plugin/issues/245/the-value-of-resolved-to-closed-kpi-is

 

0 votes
Dnyaneshwar Borase March 13, 2017

For the more details I am providing the JEP KPI for the both query for your reference.

Please refer this & let me know why this is coming up?

Thanks,

Swapnashilpa

Suggest an answer

Log in or Sign up to answer