After my collegue put a story (with a sub-task) into resolved at the kanban board the burndown chart didn't show any changes.
What's the problem could be?
We do everything the same as the other issues which effects the chart correctly.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can you verify that the issue in question was estimated correctly as well? E.g. if you burn story points, it was estimated in story points and not hours?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Are you sure that the status and resolution is correctly configured, ref. https://confluence.atlassian.com/display/AGILE/Configuring+Columns?