Tempo setup - best practices for part time resources and team planning

Deleted user March 17, 2013

I would like to use Tempo to plan work for 80 people on a software development team. I need some help with best practices.

1) I have specific requirements like managing part time resources - how do I set workday different for each user.

2) How to plan time that is initially to a team and then to an individual. I have specific reporting requirements that include viewing capacity / plan - overall, at a team and at an individual.

Please suggest the best resource to assist with setup and reporting.

Thanks!

1 answer

0 votes
Viðar Svansson [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 18, 2013

Hi Brad,

1) Have a look at the Workload Schemes in Tempo to configure each user differently.

2) It is currently not possible to create a plan without specifying a user. Please track this issue for status.

Cheers,
Viðar