I would like to use Tempo to plan work for 80 people on a software development team. I need some help with best practices.
1) I have specific requirements like managing part time resources - how do I set workday different for each user.
2) How to plan time that is initially to a team and then to an individual. I have specific reporting requirements that include viewing capacity / plan - overall, at a team and at an individual.
Please suggest the best resource to assist with setup and reporting.
Thanks!
Hi Brad,
1) Have a look at the Workload Schemes in Tempo to configure each user differently.
2) It is currently not possible to create a plan without specifying a user. Please track this issue for status.
Cheers,
Viðar