Hi Guys,
We are using Jira OnDemand with Tempo for jobsheets. I need to be able to report how much a time we have gone over on a jobsheet.
E.G Original estimate is 5h, 4h previously logged. New job set for 2h. I need to be able to report that that we have gone over by 1 hour.
Is there a way to tied this in to a tempo report or pull a worklog report with this included?
Thank you for your help
JB
Hi John,
It sounds like you would benefit from using the https://confluence.atlassian.com/display/JIRA/Time+Tracking+Report available within OnDemand. From your selected project choose 'Summary' tab, scroll down to the 'Reports' section and choose 'Time Tracking Report'.
The report includes original estimate, time remaining, time spent and accuracy.
Cheers,
Paul