Tempo Planner resource over-allocation question

Hi guys, 

I may be missing something very basic (apologies in advance if I am) but I have a question about resource allocation in Tempo Planner when it comes to over-allocation (getting a yellow line in the Planning time-line). 

Three images attached. All test data. 

Alex has been assigned to this project for 50%. (image 1) 

I then assign two stories to Alex for the same time period (Images 2 and 3). Both assignments are 50% (3.5 hours per day). This suggests that Alex is working 7h on this project during this time. But his allocation to this project is 50% (3.5 hours). 

Question: why doesn't Tempo Planner show Alex as over-allocated during this time period? 

Regards, 

Lee 

 

Screen Shot 2014-11-25 at 12.26.14.png

Screen Shot 2014-11-25 at 12.26.38.pngScreen Shot 2014-11-25 at 12.26.14.pngScreen Shot 2014-11-25 at 12.26.46.png

 

 

1 answer

Hi Lee

Over allocation is calculated based on the persons commitment according to their workload scheme, and not to their availability in the team. According to this Alex will not become over allocated untill plans are made for over 100% (which in his case is 7 hours). If Alex would only be working part time for 3.5 hours according to the workload scheme, he would become over allocated when planned for more then 3.5 hours.

 For more information on workload schemes please see: https://tempoplugin.jira.com/wiki/display/TEMPO710/Workload+Schemes

I hope this has been helpful.

Best regards,

Heiða Dóra

Tempo Team

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

Looking for anyone who made the switch to Data Center

The Jira Marketing team is putting together an ebook on migrating to Data Center. We're looking for pro tips on how you staffed your project team and organized your Proof of Concept. Share yo...

38 views 0 2
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you