Tempo Plan Time Function and Done Status

Cristian Orsini January 23, 2014

Hi all,

I'm using the Tempo Plan Time function when I assign a task to a user in my team.

I need the task disappears from the Plan Time Timesheet when the user set the task up on "done" status if the task is in the Plan Time Timesheet of the following days.

Eg:

I set the task "A" in the Andrew's Plan Time of today and tomorrow.

Andrew works the task then sets the status up on "done" today.

In the Andrew's Plan Time of tomorrow the task "A" should not be in, because the task has been solved today.

Is possible do this automatically?

Thanks,

Best regards.

1 answer

1 accepted

0 votes
Answer accepted
Susanne Götz [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 26, 2014

Hi Christian,

This is not supported in our current Tempo Timesheets version. We value feedback and comments on how we can make Tempo better, so if you have a feature request, please create an issue in our Atlassian JIRA (https://tempoplugin.jira.com/browse/JTMPO).
Other users with similar requests can vote on these issues and contribute by adding comments that will help Tempo developers implement the request.

Kind regards,

Susanne

Suggest an answer

Log in or Sign up to answer