Hi,

We want to use tempo for timesheet validation.

Our user structure is :

Development Manager

-> Team Lead 1

-> Team User 1.1

-> Team User 1.2

-> Team Lead 2

-> Team User 2.1

-> Team User 2.2

We want the Team Leads to plan time and approve timesheets for their users, and the development manager to plan time and approve timesheets for everyone.

Is there a way to achieve this?

Thanks

Stéphane

1 answer

0 votes
Susanne Götz [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 25, 2014

Hi Stéphane,

To make the Plan Time button available in the Timesheet view, you will need to check the "Enable Time Planning" in the Tempo Global Configuration.

The Team lead can then plan time for users and Team lead includes the Approve Timesheets permission.

You will need to add the Development Manager to the Approve Timesheets permission so he will be able to give him access to plan and approve.