Team Planner - Plan item type by sprint?

Casey McCluskey December 29, 2016

When in Team Planner, I am unable to have any sprints populate.  Can type the sprint out by hand and it still will not populate.2016-12-29_7-28-36.png

2 answers

1 vote
Tempo Support
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 29, 2016

Hi Casey,

can you confirm that the Team you are planning for is linked to an Agile Board (Team, Configuration, Links) as only Sprints of linked Boards are available in this dropdown.

In case this is not what is causing this problem, can you create a ticket in our Tempo Support (https://support.tempo.io/hc/en-us/requests/new) so we can better investigate this.

Regards,

Susanne Götz
Tempo team 

0 votes
Casey McCluskey December 29, 2016

Thanks Susanne, that was definitely what was causing the issue.