One of my team member has a task assigned to him, it is showned in the backlog for the curren sprint, but in the view "Active sprint" it doesn't show up.
Leading work group and Active sprint are correct.
Basically, I'm wondering whay we can see it in the backlog for current sprint but not in Active Sprint?
Hi @Johan ,
You can try to check the following configurations:
1. Column: Is there an Unmapped status, Issues in these statuses won't show on the Kanban board or Kanban backlog .
2. Quick Filters: Is there a Quick Filters to hide the issues ?
Hi,
Please move the Task from "Backlog" to "Active Sprint" in "Backlog" tab.
~Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have you performed the "Integrity Checker" and "background reindex" ? How was the result after that? Most of the time Integrity checker fixes these type of cache issues in Jira.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, those integrity checker activity needs Jira tool administrator access.
Regards,
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I am facing the same issue. Does anyone have a resolution for this ?
My issue is found in the backlog, but not found in the active sprint.
Note: the issue is tagged to multiple sprints in which it could not be completed so now in the latest sprint it is not to be seen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.