We have a client where we encountered the following situation:
We would love to fix this ASAP, does anybody have a clue what's going on there?
Mystery solved: never trust an user who says: "I didn't do anything!".
The client actually modified the reporting period (changed the start of the working week from Monday to Sunday). Therefore, all timesheets start date do not match => the behaviour above.
(!and thanks to the TEMPO team for their fast escalation!)
Certainly not the expected behavior. Something else might have happened. You might want to reach out to Tempo support!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I've done that ... thanks! But I thought that asking around cannot hurt :)