Summary Page Board -- Overall Estimate Sumup

Felix Babin-Ebell
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 10, 2024

Hello,

I'm quite new to Jira. We are using the Project Part with Boards.

 

On the summary page, I get a Overview of how many tasks are in what bucket.

 

456.png

 

Is there any possiblity to add up all the original estimates of time?

 

For example: 29% of all tasks in on hold, 6 tasks total, 8w 4d estimate total?

Thank you for your help!

Felix

 

1 answer

0 votes
Danut M _StonikByte_
Atlassian Partner
December 11, 2024

Hi @Felix Babin-Ebell,

Welcome to the community!

I'm afraid that it is not possible to sum-up the estimation fields in Overview.

An possible option would be to search for a plugin on Atlassian Marketplace that is capable to sum-up a field.

If you are willing to try a plugin, our Great Gadgets app offers a Pivot Table & Pivot Chart gadget than can easily calculate this for you and display as a table, heat-map table or charts of various types. 

See some examples:

image.png

image.png

Danut.