I don't know if is possible to configure this question.
When I have a Story with for example 2 subtask, I put the story points in the subtask
- Subtask 1 = 3 Story points
- Subtask 2 = 2 Story point
I need to see in the history the sum of his subtasks automatically, Stoy -> Story points = 5
Is this possible?
Thanks and regards
This can be done with automation rules. See https://community.atlassian.com/t5/Marketplace-Apps-Integrations/How-can-you-automatically-sum-the-story-points-of-all-subtasks/qaq-p/863364
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
oooh, yes i see the hours sums but we need to sum the story points too :(
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lorena
Using the standard Jira Story Points field, this isn't possible.
The expectation (and the way that most people use Task -> Subtask) is that you agree on story points for the story (or parent item) and then each subtask is estimated in hours - the estimated hours sums to show the total on the parent.
Hope this helps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.