Sum story point in subtasks

Lorena Muns January 30, 2019

I don't know if is possible to configure this question.

When I have a Story with for example 2 subtask, I put the story points in the subtask

- Subtask 1 = 3 Story points

- Subtask 2 = 2 Story point

 

I need to see in the history the sum of his subtasks automatically, Stoy -> Story points = 5

Is this possible?

 

Thanks and regards

3 answers

Scott Fletcher June 16, 2020

Ah!  Finally a real solution!  Thank you!  

0 votes
Lorena Muns January 30, 2019

oooh, yes i see the hours sums but we need to sum  the story points too :(

Jayashree bai December 18, 2019

Any solution for this?

0 votes
Warren
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 30, 2019

Hi Lorena

Using the standard Jira Story Points field, this isn't possible.

The expectation (and the way that most people use Task -> Subtask) is that you agree on story points for the story (or parent item) and then each subtask is estimated in hours - the estimated hours sums to show the total on the parent.

Hope this helps