Subtask option not available in Teambased project even after creating it.

Renjini June 7, 2022

Couldnot see the option to add subtask in a story. Its already created in the issue type

 


 

1 answer

0 votes
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
June 14, 2022

Hello @Renjini

Thank you for reaching out.

Can you please confirm if your site has not disabled the sub-task hierarchy as described in this documentation?

You can check this by following the steps below:

  1. Select > Issues.

  2. Under ISSUE TYPES, select Sub-tasks.

  3. Click Enable or Disable sub-tasks as needed:
    Screen Shot 2022-06-14 at 17.06.46.png

Let us know if this information helps.

Suggest an answer