Sub- Task with automated assign "TO DO" status

Magdalena Migas February 26, 2020

Dear All, 

 

I would like to create a rule where I could skip first "New" status and receive  Sub-Task already in " To Do"  status. 

Should I use the Post Function method or maybe it is a different way to set up it?

 

Thank you in advanced :)

1 answer

1 accepted

0 votes
Answer accepted
Jakub Sławiński
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 26, 2020

No, it is much easier.

 

You should simply update the 'create' transition for sub-task to set the destination step to 'to do'.

Magdalena Migas February 26, 2020

Hi,

 

Am I understand it correctly Workflow -> 'Create" transition line -> post function ? 

Like Vladimir Matveev likes this
Jakub Sławiński
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 26, 2020

No,

 

Workflow -> 'Create' transition line -> whatever -> edit

 

You should go to 'Update Workflow Transition':

 