Is there a way to add another tab in Structure that will show estimated time less time spent on a particular task. When time spent on a task is above the estimate there is no column to show the overage.

1 answer

0 votes
Robert Leitch [ALM Works]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 11, 2015

Hi Darryl,

Sorry for the late reply (it's only been a year) - we monitor Atlassian Answers using our plugin tags (e.g. 'structure' and 'addon-com.almworks.jira.structure') so I'm afraid that questions without them often get missed. I added one of our tags to this question so we can find it later if we need to smile

You can add your own custom columns to Structure with a bit of coding.

 

Best,

Robert