Strange burndown chart view missing ideal line (guideline)

Hi, I have a problem with the ideal line (guideline) in my burndown chart. It is missing and it is NOT because I add stories after the sprint started.
If I look at the Sprint log file below the burndown chart, I can see that Jira Agile used the time I 'created the Sprint' as the 'Sprint start' time. So, in this case I created the sprint at 12:00pm before the Sprint planning meeting. The Sprint backlog got filled during the Sprint planning meeting and I 'started' the Sprint at 03:00pm after the Sprint planning meeting.

IMO this is a bug or am I doing someting wrong? Time should only start ticking when I hit the SPRINT START button. Where would you suggest to file issues like these? best,

4 answers

1 accepted

Easy fix is to set the start time of the sprint to a future point in time. Then everything is caluculated correctly

I'm having this same problem as well.

0 vote

Yup, setting start date to past was the problem. Edit the sprint and have it start today fixed it.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Sunday in Agility

You asked for it, so we delivered: images on issues have arrived

A picture tells a thousand words. And agility boards have just released their latest feature: cover images on issues – so now your board can tell a story at first glance. Upload attachmen...

891 views 3 12
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you