Story points, subtasks, burndown chart?

Hi All,

I am confused about how burn down and velocity charts work in JIRA. 

We use hours for story points. So I understand the velocity and burn down are calculated as we close the stories. 

So if the Time Tracking is on, does it calculate these even if the stories are not closed?

How are velocity/burn down values calculated?

Thanks.
Eshan

1 answer

1 accepted

1 vote
Accepted answer

Basically, what is the relationship between story points and time tracking?

There is no relationship.  Time tracking is a record of estimated time worked and actual.  Story points are a measure of complexity.

A burndown chart can be told to use one of them (or another number) to track how you're doing.

Subtasks are irrelevant to burndown - they are a convenience for developers to break down a story, but can't be used for progress tracking.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 08, 2019 in Jira

How to Jira for designers

I’m a designer on the Jira team. For a long time, I’ve fielded questions from other designers about how they should be using Jira Software with their design team. I’ve also heard feedback from other ...

1,095 views 4 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you