Story in sprint (To Do) show 0 sub-task even if there are subtasks

Helen Ahlberg May 23, 2019

I have 4 Stories in a sprint (in To Do) all showing this even if there are sub-tasks in alla of them. Why? The board filter only says: project = SMU and the Quick filter only has a selection of Epic Link (all correct showing)

 

smu sprint 3_11 subtasks.png

2 answers

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 25, 2019

Annoyingly, the epic link does not cascade down to sub-tasks, so if you use "Epic link = X" or even "Epic link is not empty", it will exclude the sub-tasks, as they don't have it.

0 votes
Brian July 22, 2021

I encountered a similar problem. Except it wasn't and Epic Link or Quick Filter related. 

  1. When accessing the active sprint (which used swimlanes = stories) and clearly the subtasks were present in this view...
  2. open a subtask from the sprint board
  3. from the subtask view click on the story number inn the upper left corner
  4. then close the story

This would result in all story swimlanes being collapsed and all subtasks of the stories to read zero (just like the original post. Clearing my cache fixed the issue.  