Story estimation not updated from the portfolio

When I create stories in the portfolio and then select Create and link issues from the Epic the stories are created in the project but the Estimate field is not updated. It doesn't get updated when I select Plan>Apply updates to project/s either. Am I missing any configuration?

Thanks in advance for any help.

image2015-3-13 10:42:28.png

 

1 answer

Figured out this one.

Board>Configure. Select the estimation option and set Estimation Statistic to Original Time Estimate and Time Tracking to Remaining Estimate and Time Spent.

image2015-3-13 11:2:8.png

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 08, 2019 in Jira

How to Jira for designers

I’m a designer on the Jira team. For a long time, I’ve fielded questions from other designers about how they should be using Jira Software with their design team. I’ve also heard feedback from other ...

1,212 views 5 10
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you