When I create stories in the portfolio and then select Create and link issues from the Epic the stories are created in the project but the Estimate field is not updated. It doesn't get updated when I select Plan>Apply updates to project/s either. Am I missing any configuration?

Thanks in advance for any help.

image2015-3-13 10:42:28.png

 

1 answer

Figured out this one.

Board>Configure. Select the estimation option and set Estimation Statistic to Original Time Estimate and Time Tracking to Remaining Estimate and Time Spent.

image2015-3-13 11:2:8.png

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

26,070 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you