Story Points vs Estiamtes

We have been using Story points wrong. We currently use Story Points as an estimate of hours it will take to complete the task. The developers then log their hours spent, but we can't use the Time Tracking Report because story points are not really meant to be a measurement of time(correct?). 

 

How should we go about moving all of our story points to Time Estimates?

1 answer

0 vote
Warren Levy Community Champion Jan 11, 2018

Hi Ryan

Yes you're correct that Story Points are not directly related to time  and should not be used as such.

When you ask about moving SP to time, are you meaning all current (open and closed) Jira issues? Or is this more of a Scrum question about how to transition the team's thinking about SPs? The answer to this should help people to answer correctly

Thanks Warren. I do mean that I would like to move all existing open and closed SPs to the Original Estimate field. 

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Tuesday in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

523 views 1 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you