Story Points vs Estiamtes

We have been using Story points wrong. We currently use Story Points as an estimate of hours it will take to complete the task. The developers then log their hours spent, but we can't use the Time Tracking Report because story points are not really meant to be a measurement of time(correct?). 

 

How should we go about moving all of our story points to Time Estimates?

1 answer

0 votes
Warren Levy Community Champion Jan 11, 2018

Hi Ryan

Yes you're correct that Story Points are not directly related to time  and should not be used as such.

When you ask about moving SP to time, are you meaning all current (open and closed) Jira issues? Or is this more of a Scrum question about how to transition the team's thinking about SPs? The answer to this should help people to answer correctly

Thanks Warren. I do mean that I would like to move all existing open and closed SPs to the Original Estimate field. 

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,026 views 12 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot