Starting a sprint throws a warning message

Shneor Cheshin April 25, 2016

Hello!

I am trying to start a sprint and getting the error/warning below.

Any ideas why?

How to resolve?

You will not be able to complete this sprint, as it includes sub-tasks that cannot be transitioned to the "Done" column.

2016-04-25_15-09-01.png

JIRA v7.0.4


Thanks!

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 25, 2016

Your workflow for sub-tasks is incorrect, OR your column mappings are incorrect.

Have a look at the board config first - what status are in the "done" column?

Now look at the workflow for each type of sub-task in the project - at least one of them will not have any status that you noted were in the "done" column.

Shneor Cheshin April 25, 2016

Cheers Mate!

For some reason board creation failed.

So actually I did not have a board for this project to support the sprint :|

I re-created the board and voila... things are working again.

 

Thanks