Start/End date being changed by the 'wrong'/random user

Ian Hill December 3, 2018

In the last couple of months we have had a few instances of JIRA tickets being updated with start date/end date changes by users who swear blind that they did not make those changes

None of the examples seem to be in tickets that are linked to another ticket, so it doesn't appear to be an automation of any sort (well, not on the face of it)

And it's not always the same person who appears to have made the changes

1 answer

0 votes
Payne
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 3, 2018

If you have ScriptRunner installed, check the Escalation Services. I'd also check any Service Desk project Automation sections as well, as linkage to another ticket is not a requirement.