Hello all.
I have been struggling with the Sprint Report for some days but I don't seem to find a solution.
We have around 10 projects on our Jira instance and for all of them we are running bi-weekly sprints. Whenever we complete sprints for these projects we are checking "Sprint Report" and the same behaviour appears.
Some of the issues do not appear on the report even being associated to that sprint, they do not show up as "completed" nor "not completed"
Can anyone throw some light into this, we may be missing something but we cannot figure what.
Are you still working on this issue?
If so, there are two common reasons for this symptom: either the issues are not marked as resolved correctly or the underlying items or filter have changed.
Regarding resolved, check your scrum board's columns, and confirm that the resolution is set when items move to the last column on the board.
Regarding filters, copy your filter and test it with Issues and Filters to determine if it returns the results that you expect. If not, determine where the difference is to update the filter.
Best regards,
Bill
Hey @Bill Sheboy I also have been facing the same issue with my sprint reports. The status for the issue is marked correctly, and there are no filters associated to this board im working with but many issues dont appear on the report even though we have completely finished them in the sprint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
First thing, I recommend creating a new question and linking to older ones for context. Otherwise only the people following this thread will see it, limiting the number of suggestions offered. Thanks!
Next, for Jira Scrum boards the velocity report considers issues as done when the status is mapped to the right-most column of the board. Is that the case for your board?
Kind regards,
Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think I can add a point to the question: I do not see issues assigned to epics from different project.
If I add that other project to the board filters, it would automatically add sprints from that other project to the board, and impede ability to start new sprints of local project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Forgot to mention the actual solution: either reassign the issue to an epic from the same project, or migrate epic to the project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
One of my teams was having the same issue.
In the Board settings -> Estimation, the estimation method was not set. Once it was set to "Story Points" all of the data showed up.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.