Sprint Report is show correctly but in release burndown its showing wrong information.

Revital Kristal July 24, 2017

On the release burndown report I see no issues were completed for some of my sprints, but when I look on the sprint burndown I can see that must of the tickets are completed. Why? How can I solve it so the release burndown will show me the real image of the release status?

 

1 answer

0 votes
Yugank Bhatnagar July 27, 2017

I would suggest to check if you have selected the relevant release version in Release burndown if there are multiple releases .  As release burndown shows how your team is progressing against the work for a release

Revital Kristal July 29, 2017

Thank you for your answer. I checked, and I have selected the right release. I still see only part of the sprint associated with the release :(