Sprint Report is show correctly but in release burndown its showing wrong information. Edited

On the release burndown report I see no issues were completed for some of my sprints, but when I look on the sprint burndown I can see that must of the tickets are completed. Why? How can I solve it so the release burndown will show me the real image of the release status?

 

1 answer

I would suggest to check if you have selected the relevant release version in Release burndown if there are multiple releases .  As release burndown shows how your team is progressing against the work for a release

Thank you for your answer. I checked, and I have selected the right release. I still see only part of the sprint associated with the release :(

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

23,809 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you