Sprint Health Gadget hours per day do not match issue hours per day

Andrew.Whitfield May 24, 2022

My JIRA Sprint Health Gadget hours per do do not match issue hours per day.

The number of hours for 1 day when logged against an issue is 6 hours.

The number of hours on the Sprint Health Gadget does not change to 1 day until there is at least 8 hours logged against an issue.

What do i need to do to have the Sprint Health Gadget show 1 day for every 6 hours.

snagit1.pngsnagit2.png

1 answer

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 24, 2022

Welcome to the Atlassian Community!

This is down to the "working hours" that Jira looks at in the time-tracking functions.  The sprint gadget is "prettifying" the number into your settings for working days.

Go to Admin -> Issues -> time tracking and check what you've got set for the working day.  I suspect you've got the default of 1 week = 5 days = 40 hours (8 hours a day)

Andrew.Whitfield May 24, 2022

Thanks Nic, i can check that out (I don't have Admin access) but my assumptions was that working hours is set at 1 week = 5 days = 30 hours, as when i type 1d in the original estimate time in an issue at converts to 6h.