Sprint Completed - Sprint Report not updating with new Issue Status Edited

Hi,

 

I'm trying to use the Sprint report for the rollout of my issues, so have three status under "Done" = "Closed", "Ready for Live" and "Rollout Complete". 

 

I have just amended the status of an issue from "Ready for Live" to "Rollout Complete", however my Sprint report is not relfecting this.

 

Can Sprint Reports react to changes within an issue after the Sprint is compelted? 

 

 

Thanks,

 

 

1 answer

This widget could not be displayed.
Tarun Sapra Community Champion Aug 10, 2017

Sprint report won't reflect issue changes once the sprint is complete.

Ah. 

So currently I'm having to track Rollout off-system - is there any way of doing this (tracking issues after a sprint) through JIRA?

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

139 views 2 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you