Sprint Burndown Chart Broken??

DJ Khanmamedov February 22, 2019

I started my sprint 2 days ago. but it looks broken (upside down).  What is the issue here?

Please see attached image.

 

Burndown.PNG

1 answer

1 accepted

0 votes
Answer accepted
Randy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 22, 2019

Looks like you added scope (or increased estimates) on Feb 20, Feb 22, and removed scope, closed issues, or reduced estimates on feb 22.

 

What's the problem?

DJ Khanmamedov February 22, 2019

Thanks Randy.  I was expecting JIRA to automatically rebaseline and adjust the gray line. 

 

I guess my main question: where/how do I rebaseline the Sprint?

Erez Morabia February 22, 2019

There is no way that I know of to rebaseline the Sprint. Once you have started the Sprint there is no way to go back. This is why it is important to do the Sprint Planning before starting the sprint, and making sure all stories have story points.

Cheers! 