Sprint Burn-Down by Hours instead of by Story Points

Hi,
Is it possible to do a Sprint Burndown chart that is based on tasks rather than story points ? And specifically hours on those task's original estimates rather than Story Points for the parent Story ?
Regards
Michael

1 answer

Yes you can! If you have the correct permission, go the "Board > Configuration > Columns > Estimation" then choose what setting do you like smile

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Jira

5 ways you can make the most of Jira Software and Bitbucket Cloud

As part of the Bitbucket product team I'm always interested in better understanding what kind of impact the use of our tools have on the way you work. In a recent study we conducted of software devel...

102 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you