Setting remaining estimate to 0

Christoffer Högdén August 8, 2012

Hi,

I have a problem, we would like all our remaning estimates to be 0 when an issue is being closed. However, when I add a post funtion that set remaining time to 0 when issue is beeing closed, the orignal estimate also gets set to 0 as well which messes up our follow-ups through the hour burndown charts.

Is there anything I can do to avoid this? Is it a known bug, would upgrading solve the issue?

Regards,

Christoffer

1 answer

0 votes
Vishnukumar Vasudevan
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 8, 2012

May I know your JIRA version ? It works for me with JIRA 4.4.5.

Christoffer Högdén August 8, 2012

sure, we re using version 4.4.1