Setting Due Date based on Create and custom field

Warren Hoppmeyer June 28, 2017

We continually reusing a project and its issues over and over having to go in and manipulate all of the issue create dates. I've created a custom field Days to Complete (a number value such as 14).

I'd like to have Due Date for all Tasks and subTasks in the project update based on Create Date plus Days to Complete value. 

Anyone able to help?

1 answer

0 votes
Nadir MEZIANI
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 30, 2017

Hi,

You can do it using a scripting plugin of Jira like JJUPIN or Sciptrunner

Or you can do too in the database but you have to shutdow Jira.