Hi all,
i am new with JIRA administration. Former I was using it as a developer.
Our Plan:
1. everybody defines issues
2. issues get separated in subissues
3. our projekt adminstrator plans our sprints by issues which have an estimation.
our Problem:
Subissues cannot get an estimation...
Is there any way to setup an estimation?
Regards
We use JIRA on *.atlassian.net. Could not even find the option mentioned in the second of your links
"Choose > Issues. Select Screens > Screen Schemes"
Sub-tasks can get an original estimate on them, if you add the time tracking fields to the screens corresponding to sub-tasks. and you can add time estimates by editing the sub-task.
However, if you are using jira-agile then it is a different story altogether.
Go through these links to familiarise yourself to the concepts of adding fields to screens
https://confluence.atlassian.com/display/JIRA/Configuring+Fields+and+Screens
https://confluence.atlassian.com/display/JIRA/Associating+a+Screen+with+an+Issue+Operation
https://confluence.atlassian.com/display/JIRA/Defining+a+Screen
Pilar