Scheduled Task Start Date

Do I have the ability to create Start Dates for Scheduled Tasks?

I am trying to figure out the best way to schedule tasks for production.

I know I have the option to use the have the fields: Created, Updated, Due Date. I wouild like to schedule and assign tasks prior to their actual start date.

2 answers

I would suggest a custom StartDate field with an additional status ("Not Started"), then you could use a jelly script to update the status to "Open" when the StartDate is reached.

You could even add an userpicker field to store the future assignee and leave the issue unassigned and the assign it at the StartDate.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Jira

5 ways you can make the most of Jira Software and Bitbucket Cloud

As part of the Bitbucket product team I'm always interested in better understanding what kind of impact the use of our tools have on the way you work. In a recent study we conducted of software devel...

78 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you