Roll up Story Points and Time (actual) to Initiatives

In my JIRA project, we have the following issue hierarchy:

Sub-tasks > Stories > Epics > Initiatives

 

Most of our estimates and tracking happen at the Story level:

  • Story Points are recorded on Stories
  • Time estimates are recorded on Stories or Sub-tasks

I am hoping to run some reports aggregating up the Initiative level, to report on story points per initiative (per time frame) and actual time spent.   Would love any advice or recommendations on how to do that!

2 answers

Benj - Did you ever get an answer?  I am looking to do the same thing and would love to hear any suggestions that worked.

I was looking for an answer also. 

The best I could find so far was to use the Portfolio view, and in it, use/show one of the Estimates columns. In the portfolio view, the times will add up to all levels of the hierarchy.

If somebody has a better answer please share!

Suggest an answer

Log in or Sign up to answer
Community showcase
Published 8 hours ago in Jira

How you can achieve compact and easy-to-maintain workflows in your JIRA( Server)

This approach requires you to have the JIRA administrative rights. The main aim of this article is to help you achieve an organized, easy-to-maintain workflows in your JIRA instance thereby, reducin...

104 views 0 0
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you