Resolved Issues are being rolled when the sprint ends

We are experiencing an issue where work that has been resolved (but which is not closed) is being rolled automatically into the next sprint. I think it is affecting the velocity charts, as well.

Please help!

2 answers

This widget could not be displayed.
This is exactly what is supposed to happen. Agile considers issues "done" in the done column and only allows done issues in sprints as they close. It tries to be helpful by moving not-done issues into the next sprint because that is what you should do. You need to clear up your understanding of "done", or not create the next sprint until the current one is ended (not-done issues go back into the backlog of you do that)
This widget could not be displayed.
This is exactly what is supposed to happen. Agile considers issues "done" in the done column and only allows done issues in sprints as they close. It tries to be helpful by moving not-done issues into the next sprint because that is what you should do. You need to clear up your understanding of "done", or not create the next sprint until the current one is ended (not-done issues go back into the backlog of you do that)

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

141 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you